A1 Highway Lugoj – Deva

Highway Length: 28.6 km Overpasses: 9 Bridges: 2 Total Project Value – Lei: 562,730,583.80 RON Total Project Value – Euro: aproximativ 128,000,000 € Status: in execution Western Romania Providing Construction Supervision and Contract Management services for 28.6 km, Section 2, to improve traffic flow for travel, tourism and commerce. The Lugoj – Deva highway is…

Piers’ Modernization – Jiu River

Length: 11.76 m Pier Crossing Flood Defense Total Project Value – Lei: 7,385,600 RON Total Project Value – Euro: aprox 1,649,420 € Status: finished Gorj County, Southwestern Romania Providing preliminary to final construction drawing design and technical assistance for necessary rehabilitation and modernization of piers on the Jiu River. As a result of rains, the…

Braila Port Quays at Wharf 23 & Wharf 25

Braila Port – Danube River – Eastern Romania Providing preliminary to final construction drawing design and technical assistance to quays for port modernization. Part of the POST program (Operational Sectorial Transport Program) whose main objectives are to modernize and develop the national transport network in Romania. Completed 10 months ahead of schedule, Consitrans was responsible…

Ciurel Suspension Bridge

Bridge Length: 3.56 km Highway Length: 6.44 KM Bridges: 14 Total Project Value – Lei: 562,730,583.80 RON Total Project Value – Euro: aprox 128,000,000 € Status: in progress Bucharest, Romania Providing Construction Supervision and Contract Management services for the Ciurel Suspension Bridge, part of a much larger expressway project that will connect Independence Pier Road…

Piata Presei Libere Underground Passage

Length: 1.134 km Ramps: 3 Exits: 2 Total Project Value – Lei: 562,730,583.80 RON Total Project Value – Euro: aprox 128,000,000 € Status: finished București, Romania Providing Preliminary to Final Design Services and Technical Assistance for an underground passage in Bucharest, facilitating traffic flow in the nation’s capital. This underground passage at Bucharest’s exit comprises…

“Mihail Kogalniceanu” International Airport

Area: 155,253 square metres Passengers: 80,000 Taxiways: 2 Total Project Value – Lei: 82,625,695 RON Total Project Value – Euro: aprox 18,486,149 € Status: finished Constanta, Eastern Romania Providing Construction Supervision and Management for the rehabilitation of taxiways and platforms increasing safety and comfort of passengers as well as travel. The “Mihail Kogalniceanu” Airport is…

Bucharest Ring Road – South

Length: 10 km Overpasses: 3 Intersections: 3 Total Project Value – Lei: 1,760,000 RON Total Project Value – Euro: approx 47,047,784.3 € Status: finished Bucharest, Romania Providing preliminary to final engineering design to modernize 10km of the southern portion of the capital’s ring road to improve traffic handling capacity, redistributing traffic and decongesting city streets.…