A7 Highway – Ploiesti – Buzau

Highway Length: 63.25 km Overpasses: 40 Junctions: 6 Maintenance centers: 2 Parking-service spaces: 4 Status: Feasibility Study – finished Technical Project – in work https://consitrans.ro/wp-content/uploads/2021/03/consitrans-buzau-ploiesti.mp4 A7 Highway – Ploiesti – Buzau For this project we provided the analysis for the best highway positioning and layout, followed by the Feasibility Study and Technical project. Part of…

Sulina Port – quay modernization

Quay on Sulina channel : 400 m Quay on maritime basin: 400 m oncrete platform adjacent to the quays: 28.800 m2 Acces road to the street network of Sulina: 650 m Dredging of the acces area for the quays https://consitrans.ro/wp-content/uploads/2021/07/Modernizare-Cheu-Sulina-25-06-2021.mp4 Sulina Port – quay modernization This feasibility study proposed and integrated modernization of the port…

10 Ports – Danube River (Maritime)

Danube River – Eastern Romania Providing a feasibility study of 10 ports on the Maritime Danube River in order to stimulate rehabilitation of the naval infrastructure. The ports on the Maritime Danube River, Sulina, Tulcea, Galati, Braila, the ones on the secondary channel, Mahmudia, Chilia Veche, Macin with loading docks Turcoaia and Gura Arman as…

12 Ports – Danube River (Fluvial)

12 Ports Piers: 16.200 m 7 TEN-T Ports Danube River – Eastern Romania Providing a feasibility study 7 TEN-T ports and 5 ports outside the TEN-T network on the Danube River in order to stimulate rehabilitation of the naval infrastructure. The ports on the fluial Danube River have over 16,200m of piers, of which 20%…

Piers’ Modernization – Jiu River

Lungime: 11.76 m Chei de trecere Apărarea împotriva inundațiilor Valoare totala – lei: 7,385,600 RON Valoare totala – euro: aproximativ 1,649,420 € Status: finalizat Gorj County, Southwestern Romania Providing preliminary to final construction drawing design and technical assistance for necessary rehabilitation and modernization of piers on the Jiu River. As a result of rains, the…

Braila Port Quays at Wharf 23 & Wharf 25

Braila Port – Danube River – Eastern Romania Providing preliminary to final construction drawing design and technical assistance to quays for port modernization. Part of the POST program (Operational Sectorial Transport Program) whose main objectives are to modernize and develop the national transport network in Romania. Completed 10 months ahead of schedule, Consitrans was responsible…

Ciurel Suspension Bridge

Lungime pod: 3.56 km Lungime autostrada: 6.44 KM Poduri: 14 Valoare totala – lei: 562,730,583.80 RON Valoare totala – euro: aproximativ 128,000,000 € Status: in lucru Bucharest, Romania Providing Construction Supervision and Contract Management services for the Ciurel Suspension Bridge, part of a much larger expressway project that will connect Independence Pier Road to the…

Piata Presei Libere Underground Passage

Lungime: 1.134 km Rampe: 3 Ieșiri: 2 Valoare totala – lei: 562,730,583.80 RON Valoare totala – euro: aproximativ 128,000,000 € Status: finalizat București, Romania Providing Preliminary to Final Design Services and Technical Assistance for an underground passage in Bucharest, facilitating traffic flow in the nation’s capital. This underground passage at Bucharest’s exit comprises of a…

“Mihail Kogalniceanu” International Airport

Suprafața: 155,253 metri pătrați Pasageri: 80,000 Căi de rulare: 2 Valoare totala – lei: 82,625,695 RON Valoare totala – euro: aprox 18,486,149 € Status: finalizat Constanta, Eastern Romania Providing Construction Supervision and Management for the rehabilitation of taxiways and platforms increasing safety and comfort of passengers as well as travel. The “Mihail Kogalniceanu” Airport is…